Ontario Power Generation says first Darlington small modular reactor will exceed C$7.7 billion budget and miss October 2030 target
By Eve
Ontario Power Generation has acknowledged that its first GE Vernova Hitachi BWRX-300 small modular reactor at Darlington will exceed its C$7.7 billion approved budget and miss its October 2030 commercial-operation target, with no replacement cost or completion date yet given. The company expects its engineering, cost and schedule review to be substantially complete by mid-2027. The opinion piece cites OPG's 10 November financial results, which pointed to continuing first-of-a-kind engineering and its effects on construction execution and supply-chain performance, and argues Ontario began physical work while parts of the design were still evolving.
Why it matters
Delays and cost growth on a flagship low-carbon generation project may affect assumptions about future clean power supply for Ontario's grid, which matters to charge point operators and project funders planning long-term load and pricing. The piece also reinforces a wider lesson for procurement: design maturity and interface clarity before construction are what give schedule certainty, not visible construction progress.
Source
- Original title
- “Darlington’s First SMR Is Late and Over Budget. Ontario Needs to Rethink the Next Three.”
- Published
- 15 November 2026
- Updated
- 16 November 2026
In this story
- Topic
- Grid & Energy
- Place
- Canada
- Tag
- Ontario
Related news
Backup battery self-tests suspected of causing minute-by-minute pulsing in power grids on five continents
A team led by Dirk Witthaut, a physicist at Germany's University of Cologne, traced 60-second electrical fluctuations to uninterruptible power supplies at the Forschungszentrum Jülich campus, according to ScienceAlert citing work published in Nature Energy. Four buildings with backup power systems showed the pattern, brief bursts of battery current at one-minute intervals were tracked to the public high-voltage network connection, and the equipment manufacturer confirmed that automatic battery self-tests caused the activity. Digital clocks synchronised through external time signals appear to explain why independent systems run the checks in unison.
Why it matters
It shows how many small, battery-backed devices running time-synchronised routines can add up to measurable grid effects, a point relevant to anyone specifying or operating charging sites with onsite storage or backup power. Procurement teams may want to ask suppliers how automated battery tests and other scheduled functions are timed across a fleet of sites.
UK Government publishes clean electrification roadmap and backs two offshore wind farms
The UK Government has launched its clean electrification roadmap as the Prime Minister outlined plans to invest in two offshore wind farms. The Clean Energy Industries Sector Plan targets at least a doubling of investment in frontier clean energy industries to over £30 billion a year by 2035, with a further £700 million for Great British Energy, and the Clean Industry Bonus has used £204 million of public investment to leverage £3.4 billion of private investment in British factories, ports and supply chains. The roadmap also cites the ZEV Mandate as driving EV uptake and phasing out new petrol and diesel only cars from 2030, while ChargeUK chief executive Shane Brennan said committing to electrification whilst considering weakening EV targets is a contradiction in terms.
Why it matters
The roadmap names EV charging as an investment and jobs opportunity, but uncertainty over possible changes to the ZEV Mandate leaves demand signals unclear for CPOs and their supply chains. Procurement teams should watch how the supply chain funding and any mandate revisions shape project timelines and investment cases.
Australian Sigenergy owner sees home battery draining overnight beyond household demand, then finds a settings fix
An Australian homeowner posted on the r/SigenergyAustralia Reddit forum that their household needed only around 100 to 200 watts overnight, yet the battery system was drawing 200 to 300 watts. The setup uses an 18 kilowatt hour battery and a 10 kilowatt inverter, and a 150 watt setting for the energy saving feature had not delivered the wanted midnight to 6 a.m. sleep period. Another owner suggested a settings change as a potential solution, as reported by The Cool Down.
Why it matters
Standby and idle consumption in home battery and inverter systems can erode the savings customers expect, and commissioning defaults are a common source of support calls. Installers and operators of storage assets should treat sleep and energy saving configuration as part of handover checks.